Grid Parity

Commercial energy glossary

Grid Parity in Commercial Energy Decisions

Grid parity describes a comparison in which a generation option's electricity cost reaches a selected grid-price benchmark. For an on-site project the benchmark may be a retail rate; a wholesale project may be compared with a wholesale price. The term is incomplete without the benchmark and cost assumptions.

Compare business electricity supply

Compare to charges the facility could actually avoid

A project cost per kWh is not directly comparable with the average all-in bill price if fixed charges, minimums or some demand charges remain. Use output and self-consumption over time, then check how any exports would be credited. Include terms and costs that apply over the same analysis period.

Fictional benchmark comparison
Assumed generation cost
$0.10 per kWh
Average bill cost
$0.14 per kWh
Assumed avoidable charge
$0.09 per kWh

The example uses invented values to show why the comparison changes with the benchmark. It is not a project evaluation.

Keep the supply decision separate

Compare offers for the electricity your site expects to import. Be explicit about the amount and timing of purchases, and do not treat equipment parity as proof that a supplier contract or facility investment has a better return.